top of page
thungela  north shaft.jpg
matla.PNG

Thungela North Shaft

Greenfields project where we designed the box cut CRCP slabs, workshop, washbay, assembly area waste skips, and offices etc

Matla Decline Conveyor

Detail design of two new underground decline conveyor structures for Matla Coal Mine

Waterval Larox filters

Brownfields services for the design and detailing for the Waterval Furnace Building replacement of Larox filter presses 3 & 4

hyosong 1.jpg
thungela overland 2.jpg
waterval simms.jpg

Hyosung - Pongola and Elandskop

Eskom’s first battery energy storage project, the facility will have a capacity of 8MW, equivalent to 32MWh of distributed electricity. We were involved in the concrete designs necessary

Thungela Overland conveyor

An 8km long overland conveyor which included structural analysis of the overland modules, environmental gantries, turn tables, and ancillary structures. 3 Major culverts along with Hydraulic studies

Waterval SIMMS Inspections

Structural inspection monitoring and reporting of numerous structures at the Waterval platinum plant in Rustenburg

immediate risk structures 2.png

Sasols Rail feasibility study

Feasibility study of 52 different options for rail along with bridge positions, tippler and bunker options and conveyor options

Waterval Immediate risk Structures

As-built conveyor and building analysis for stability and strength checks according to latest codes 

Newmont Akyem

Design review of a portal structure for the entrance to a pedestrian underground tunnel

V02_S_N002_15E_B4961B_Bridge in Elevation opposite side.jpg
V02_N_B2691_Bridge in Elevation from opposite side.JPG

SANRAL Bridge Inspections

Principle inspections for SANRAL. 76 bridges in Tshwane and 48 bridges in the Eastern Cape

Western Cape Bridge Inspections

Principle inspections for both bridges and culverts in the Oudtshoorn area. 51 bridges and 148 culverts in total

WFM Silo Baghouse Structure

Brownfields projects to address the critical defects in the structure to ensure the structural stability

bin gg.JPG
kotoka.jpg
pemba.jpg

GG Stacker 2 & D8 Loading Bin

The detailed structural design review and assessment of the storm damaged and derailed stacker and loading bin for Grootegeluk Coal Mine.

Kotoka ATC Tower

External structural reviewer for the detailed design of the infrastructure at Kotoka Airport, Ghana

Pemba Airport

Structural Lead and detailed design of terminal building, ATC tower, ARFF, Mosque, ALG various buildings and  infrastructure at Pemba Airport, Zanzibar.

harmony.jpg
loesche.jpg
cardington.jpg

Harmony Audit and Scans

Scanning and auditing of SIMM’s report and developing 3D models of the plant and infrastructure with heat mapping of defects at Harmony Gold Mine.

Loesche Mill CGP Mill

Detail design of various steel structures for the installation of a new CGP plant at Anglo Waterval Smelter.

Low Hall & Cardington Street

Engineering Management services in collaboration with consultants for the development of Low Hall Depot and Cardington Street Rail upgrades in London.

Recent Projects

Achieving Goals

almalyk secondary crusher.jpg
assmang.jpg
matla silo conveyor collapse.jpg

Almalyk Secondary Crusher

The project entailed the design of structural works for a mega secondary crusher building in Uzbekistan

BRMO Rail Siding Bridge

​Detail design of the new rail siding to support higher axle loads for trains going to and from Black Rock Mine

Matla Silo conveyor collapse

Forensic analysis of the root cause of the collapse of the conveyor off the silo.

GAUTENG, SOUTH AFRICA

julia@istructeng.com

+27 82 684 5877

Ash Medical Suites and businesses 

177 Garsfontein Road, Ashlea Gardens. 

©2023 by IStructEng. 

IstructEng_WaterMark Building Greypng.png